SUBMARINE FIBER OPTIC CABLE SERVICES

Engineering, logistics and marine execution for critical subsea networks

Submarine fiber optic cable work requires precise cable handling, vessel coordination, controlled tension, marine positioning, protection of the cable system and disciplined testing. WEB combines field experience with project and logistics management to support installation, repair, burial and maintenance activities.

END-TO-END SUPPORT

Submarine cable service framework

The company profile confirms WEB experience in submarine fiber optic cable installation, repair, maintenance and cable depot managed services. The detailed framework below expands those services into a complete project lifecycle that can be adapted to the contractual scope, cable system, vessel and marine conditions.

PROJECT LIFECYCLE

Project lifecycle

01

Feasibility & Project Planning

Define route objectives, landing points, cable type, installation strategy, vessel requirements, schedule, risk register and interface matrix.

02

Route Engineering & Survey Interface

Integrate marine survey data, bathymetry, seabed conditions, hazards, crossings and burial assessment into the installation and protection plan.

03

Permits & Stakeholder Coordination

Coordinate project documentation, marine access, local stakeholders, landing activities and regulatory interfaces required for execution.

04

Cable Logistics & Depot Management

Receive, inspect, store and control cable, repeaters, branching units, joints and accessories; maintain traceability and prepare load-out sequences.

05

Mobilization & Cable Loading

Prepare vessel, loading spread, cable highway, cable engines, instrumentation, jointing area and deck arrangement; load cable to the planned sequence.

06

Marine Installation & Burial

Execute shore-end and main-lay activities with controlled pay-out, tension monitoring, navigation and appropriate burial or protection method.

07

Testing & Commissioning

Perform optical and electrical checks as applicable, verify cable integrity, document route position and close out installation records.

08

Maintenance & Repair

Respond to cable faults with fault localization, mobilization, recovery, jointing, re-lay, protection, post-repair testing and final documentation.

MARINE INSTALLATION

Installation activities in detail

Actual configuration is project- and vessel-dependent. Typical work packages may include:

Shore-end installation

Beach or landing-point preparation, shore-end pull, nearshore handling, transition to marine spread and stabilization/protection in shallow water.

Main lay

Controlled cable pay-out from tanks or carousel through cable machinery while maintaining route position, tension limits, minimum bend radius and operational speed.

Simultaneous lay and burial

Cable is laid while a plough or burial tool protects it below the seabed where soil and route conditions allow.

Post-lay burial

ROV trencher or jetting equipment follows the laid cable to achieve target burial depth in selected sections.

Protection and stabilization

Use of articulated pipe, cable protection systems, mattresses, rock placement, cement bags, clamps or other engineered protection where burial is not feasible.

Crossings and special sections

Engineering and controlled installation at pipeline/cable crossings, steep slopes, congested corridors or environmentally sensitive areas.

Submarine cable repair operation
CABLE REPAIR

Cable repair workflow

  1. Fault localization using network data and optical test information.
  2. Marine mobilization and preparation of repair spread, spare cable and jointing equipment.
  3. Cable location and recovery using appropriate grapnel, ROV or diver-supported methods depending on depth and conditions.
  4. Controlled cut, recovery and onboard handling while protecting cable bend radius and tensile limits.
  5. Jointing/splicing and electrical/optical restoration under controlled conditions.
  6. Re-lay of the repaired section with slack management and route control.
  7. Burial or engineered protection of the repaired segment where required.
  8. Post-repair testing, route verification, as-built documentation and handover.
MARINE SPREAD

Typical project equipment & systems

Equipment is selected according to water depth, cable design, burial target, seabed conditions and vessel configuration. Typical categories include:

Cable tanks, carousel or cable storage system
Linear Cable Engine (LCE) / cable engine and tension monitoring
Cable highway, rollers, overboarding sheave and stern equipment
Jointing/splicing, OTDR and optical test equipment
DGPS and marine positioning; USBL where subsea tracking is required
Plough, jet sled or ROV trencher for burial and post-lay intervention
Grapnels, cutting/recovery tools and cable handling gear for repair
ROV, cameras or diver support for inspection and protection work
CABLE SYSTEM

Cable types and system components

Submarine systems may use lightweight (LW), lightweight protected, single-armored (SA) or double-armored (DA) cable depending on depth, seabed exposure and external-aggression risk. System components can also include repeaters, branching units, beach joints, universal joints and shore-end protection.

DEPOT & LOGISTICS

Cable depot managed services

Depot management is a critical part of maintenance readiness. WEB supports cable storage strategy, inventory control, preservation, inspection, handling, load-out planning, labor coordination and delivery to the vessel so spare cable and accessories are ready when a repair window opens.

QHSE

Quality, safety and marine control

  • Pre-mobilization readiness and method statement review
  • Task risk assessment and toolbox coordination
  • Cable handling limits, tension and bend-radius control
  • Lift planning and deck safety during load-out and recovery
  • Marine weather and operational window assessment
  • Inspection and test records, traceability and as-built reporting
Subsea cable depot managed service
TRACK RECORD

Selected submarine cable experience

2022

SKKL Batam - Tanjung Batu, Riau

Cable repair activity recorded in the company profile.

2025

IKK Tarjun - Stagen Batulicin - Kotabaru

Cable repair project supporting inter-island connectivity.

2026

IKK Kotabaru - Batulicin

Repair operation followed by burial work using a jet sled.

2026

Interisland Tanjung Pinang - Galang

Repair operation and cement-bag protection installation.

2026

Sorong - Jayapura

Repair, cement-bag / clamp work and additional protection activities recorded in the company profile.

SUBMARINE WORK EXPERIENCE

Complete submarine cable work experience register

The current experience register contains 21 submarine cable work packages from 2020 to 2026. It includes main lay, shore-end work, route engineering, cable protection, fault finding, repair, spare-cable deployment, jointing, burial and inspection. Some cable systems appear in multiple entries because they represent separate work packages or separate fault events.

21Work packages listed
2020-2026Experience period
PT Infrastruktur Telekomunikasi IndonesiaPrimary client in current register
012022

Pekerjaan Main Lay dan Beach Work SKLL Inter Island Anambas-Bintan-Lingga

Location
Anambas-Bintan-Lingga
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

022020

Pekerjaan Pembangunan SKKL Inter Island Link Gili-Lombok End to End

Location
Gili-Lombok
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

032020

Pekerjaan Marine Shore End SKKL Link Gresik-Bawean dan Labuan Bajo-Raba

Location
Labuan Bajo-Raba
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
LS
Scope of Work

Not specified in current register

042020

Pekerjaan Main Lay dan Shore End SKKL Inter Island Batam Area Link Tanjung Balai Karimun- Tanjung Batu- Pulau Burung

Location
Tanjung Balai Karimun- Tanjung Batu- Pulau Burung
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

052021

Pekerjaan Marine Shore End SKKL Link Gresik-Bawean dan Labuan Bajo-Raba

Location
Labuan Bajo-Raba
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

062021

Pekerjaan Marine Shore End SKKL Link Gresik-Bawean dan Labuan Bajo-Raba

Location
Labuan Bajo-Raba
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

072021

Cable Protection dan Route Engineering Cable SKKL Inter Island Batam Area Link Tanjung Balai Karimun-Tanjung Batu Pulau Burung-Sungai Guntung

Location
Tanjung Balai Karimun- Tanjung Batu- Pulau Burung
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
2000m cable protection
Scope of Work

Not specified in current register

082021

Pekerjaan Cable Fault Finding and Cable Proetction untuk perbaikan SKKL JASUKA SEGMENT 2 Link Batam-Pontianak

Location
Batam-Pontianak
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

092024

Pekerjaan Perbaikan Gangguan SKKL SMPCS#2 Link Timika-Merauke dan LUMORI Link Morowali-BU

Location
Timika-Merauke dan LUMORI Link Morowali-BU
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

102024

Pekerjaan Instalasi Rumpon Reflector Jalur SKKL SMPCS Phase 2 Perairan Merauke

Location
Perairan Merauke
Client
PT. Infrastruktur Telekomunikasi Indonesia
Scope of Work

Not specified in current register

112025

Pekerjaan Pengadaan Jasa Perbaikan SKKL PATARA 2 Link Sarmi–BU (DOL 15.02.2025)

Location
Sarmi, Papua
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
±0.962 km repair section
Work Duration
6–14 Mar 2025 – Core Repair Operation
Scope of Work
  • Cable recovery and testing
  • SQJ Initial and Final Splicing
  • ±0.962 km repair cable deployment
  • Articulated Pipe and cement bag protection
122025

Pekerjaan Pengadaan Jasa Kapal dan Equipment, Pengiriman Spare Material dan Articulated Pipe untuk Perbaikan Gangguan SKKL Gresik–Bawean Cable System (GBCS) DOL 19.07.2025

Location
Gresik–Bawean
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
300 m spare cable laid
Work Duration
13–26 Aug 2025
Scope of Work
  • Cable finding, recovery & testing
  • SQJ Initial & Final Splice
  • 300 m MINISUB-R DA spare cable laying
  • Final testing & final bight deployment
132025

Pekerjaan Pengadaan Jasa Perbaikan Gangguan SKKL JASUKA Link Tanjung Pandan–Pontianak (DOL 26.09.2025) Menggunakan Vessel Non Cable Ship

Location
Tanjung Pandan–Pontianak
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
7.605 km spare cable laid
Work Duration
23.29 days – 24 Oct–16 Nov 2025
Scope of Work
  • Cable recovery and testing
  • SQJ Initial and Final Splicing
  • 7.605 km OCC-SC500 SA spare cable laying
  • Final cable deployment
  • Post-repair cable burial
142025

Pengadaan Jasa Perbaikan Gangguan SKKL InterIsland Lingga Ruas Lingga Utara–Senayang DOL 19.11.2025

Location
Lingga Utara–Senayang
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
136 m cable used
Work Duration
21 days (as stated in Final Report)
Scope of Work
  • Cable finding, recovery, and testing
  • 136 m replacement cable installation
  • IJC Initial and Final Joint
  • 25 m Articulated Pipe installation
  • Cement bag protection
  • System restoration to RFS
152026

Pekerjaan Perbaikan Gangguan SKKL IKK Link Kotabaru–Batulicin DOL 08.01.2026

Location
Kotabaru–Batulicin
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
284 m spare cable laid
Work Duration
17.34 days – 10–27 Jan 2026
Scope of Work
  • Cable recovery and testing
  • 284 m NSW Minisub-36 DA spare cable laying
  • MPJC Initial and Final Splicing
  • Final bight deployment
  • Cable burial/reburial
  • Post-lay inspection
162026

Pekerjaan Perbaikan Gangguan SKKL IKK Link Kotabaru–Batulicin DOL 24.01.2026

Location
Kotabaru–Batulicin
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
90 m spare cable laid
Work Duration
2.62 days Core Repair – 1–3 Feb 2026
Scope of Work
  • Cable recovery and testing
  • 90 m NSW Minisub-36 DA spare cable laying
  • MPJC Initial and Final Splicing
  • Final cable deployment
  • Articulated Pipe installation
  • Water-jet burial
  • OTDR verification
172026

Pekerjaan Post Cable Burial dengan Jet Sledge untuk Perbaikan Gangguan SKKL IKK Kotabaru–Batulicin DOL 08.01.2026

Location
Kotabaru–Batulicin
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
1.453 km cable buried
Work Duration
21 days overall; 7 days burial operation – 24 Feb–2 Mar 2026
Scope of Work
  • Pre-dive cable route inspection
  • 1.453 km cable burial using Jet Sledge
  • Burial to 1.5 m target depth
  • Telemetry burial-depth monitoring
  • Burial reporting
182026

Pekerjaan Perbaikan Gangguan SKKL SMPCS#2 Link Sorong–Jayapura (Shore End)

Location
Sorong
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
343 m spare cable laid
Work Duration
38.50 days – Actual Schedule
Scope of Work
  • Shore-end cable recovery and testing
  • 343 m OCC SC500 DA spare cable installation
  • SQJ Initial and Final Splicing
  • Final cable deployment
  • 460 m Articulated Pipe installation
  • 110 m cement bag protection using 275 bags
  • 100 m protection using 40 C-Clamps
  • System restoration and final testing
192026

Pekerjaan Perbaikan Gangguan SKKL Inter Island Tanjung Pinang–Pulau Galang DOL 17.04.2026

Location
Tanjung Pinang–Galang
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
122 m spare cable laid
Work Duration
10.18 days – 19–29 Apr 2026
Scope of Work
  • Cable recovery and testing
  • 122 m NSW Minisub-36 SA spare cable laying
  • MPJC Initial and Final Splicing
  • Final bight deployment
  • System testing
  • Cable protection
202026

Pekerjaan Proteksi Kabel dengan Cement Bag Perbaikan Gangguan SKKL Inter Island Tanjung Pinang–Pulau Galang DOL 17.04.2026

Location
Tanjung Pinang–Galang
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
220 m cable protected
Work Duration
8–24 May 2026
Scope of Work
  • 220 m cable protection installation
  • Installation of 1,300 cement bags
  • Installation of 1,834 steel clamps
  • Visual inspection and functional testing
212026

Pekerjaan Inspeksi Investigasi Perbaikan Gangguan SKKL SMPCS#2 Link Sorong–Jayapura (Shore End)

Location
Sorong
Client
PT. Infrastruktur Telekomunikasi Indonesia
Cable / Work Length
Approx. 1.11 km cable route inspected
Work Duration
28 Aug–3 Sep 2026
Scope of Work
  • Shunt-fault investigation
  • 25 Hz Tone Gun inspection
  • Diver visual inspection
  • Approx. 1.11 km cable route inspection
  • SQJ, Articulated Pipe, cement bag, and cable condition verification
SUBSEA PARTNERSHIP

Need a partner for submarine cable installation, repair or maintenance?

WEB can discuss project scope, marine spread, cable logistics, repair readiness and partnership structure.

Discuss Your Subsea Project